AFS
A 5 level underground carpark next to parliament house • Supplied 6 tower pumps for the project • Supply and placed 30,000m³ of concrete and finished 65,00m²
AMNS
13 Level building for the University of Adelaide • Supplied 2 Tower pumps • Poured 16,000m³ of concrete and finished 31,000m²
Atura Hotel
7 level Hotel at Adelaide Airport • Excavated pile caps, supplied and installed reinforcement and concrete • Poured 3,000m³ of concrete and finished 11,000m²
Bridgeport Hotel
250 bed Hotel in Murray Bridge • Poured 4,500m³ of concrete and finished 12,000m²
Brighton High School
Year 7 building as part of transition from Primary to High School • Excavate footings, supplied and installed reinforcement and concrete • Installed formwork to suspended slabs • Poured 700m³ of concrete and 2,000m²
Brougham Apartments
10 Level Apartment in North Adelaide • Poured 1,200m³ of concrete finished 6,000m²
Calvary Hospital
13 Level Hospital in Adelaide • Poured 27,000m³ and finished 60,000m²
Botanic High School
6 Level High school in the CBD • Excavate pile caps, supply and finish concrete • Poured 6,000m³ and finished 11,000m².
East End Apartments
A 6 level Apartment at the edge of the Adelaide CBD • Excavated footings, supplied, pumped and finished concrete • Installed reinforcement
GPO
20 level office building • Excavation of pile caps and footings to ground floor slab • Supplied and installed reinforcement and formwork • Poured 2,000m³ and finished 1,500m²
Kodo
30 level Apartment building • Excavation of pile caps and footings • Poured 9,500m³ and finished 30,000m²
Luminesque
7 level apartment building • Poured 1,200m³ basement slab • Poured 1,000m³ and finished 10,000m² to suspended slabs
Indigo Hotel
10 level Hotel • Excavated pile caps and footings • Poured 1,500m³ and finished 5,000m²
McAuley Schools
Year 7 building as part of transition from Primary to High School • Excavate footings, supplied and installed reinforcement and concrete • Supplied and installed suspended formwork • Poured 1300m³ of concrete and finished 4,100m²
One Apartments
21 level Apartment building • Excavate pile caps and footings • Supplied and installed reinforcement • Poured 5,200m³ and finished 14,500m²
Skycity
11 level Casino and Apartments • Poured 14,000m³ and finished 30,000m²
Toms Court
14 Level Apartment Building • Excavate pile caps and footings • Supplied and installed reinforcement • Poured 500m³ and finished 3,300m²
Unilodge
17 level Student accommodation • Excavated pile caps and footings • Supplied and installed reinforcement • Poured 5,300m³ and finished 22,000m²